@alxs Hello, please review our updated proposal. We have updated milestone 2, please let me know if you need more details or have any questions. Thanks |
|
Thanks @aliakseikulik. Could you also add deliverables 0a-e from the example milestone in the application template to yours? These are mandatory for all milestones, which apparently we forgot to mention at the time of the last amendment. |
|
Pinging @aliakseikulik |
|
@aliakseikulik note that given the repeated delays and unresponsiveness from your side, we will see ourselves forced to cancel the grant if we don't hear from you within the next week. Please address my feedback above. Note that this amendment to submit by the end of the month has yet to be approved. |
|
@alxs hello guys, I apologize for delay. Will submit updates today. Thank you |
Add mandatory 0a-0e deliverables
|
Hi @aliakseikulik, thanks for the update. Is the target delivery date of end of December still in effect? You are free to update it, given that this PR is now a month old. |
Hi @semuelle . We are still targeting the end of December and doing our best to deliver in time, but due to holidays, full delivery (including all deliverables like articles, etc.) may happen a week or two later. Should I update? |
|
Make it end of January, no need to be stingy. |